FACTORY EXTENSION UPDATE (October)
Since the last extension update in August, the new factory area is nearing completion. The floor, canteen, goods-in office, electrics, alarm and sprinkler systems are now all in place and plans to move teams and machinery will commence on Monday 9th October.
Also completed within the last month is the newly laid carpark and exterior of the new Research and Development office. Plans for furnishing the new office block and completion of the whole development project are due to be fully operational in mid October.
View the pictures below to see the progress to date.
Tarmac laid for new carpark (21 Sept 06)

Carpark finished (25 Sept 06)

Electrics installed in new area (25 Sept 06)

New R&D Office exterior finished (2 Oct 06)

Keep re-visiting the news page for regular up-dates.